Owner: Illinois Department of
Transportation
Contract Amount: Approximately
$39 Million
Location: Bloomington-Normal,
IL
Description: This project consisted
of the reconstruction of the interchange of Business 55 (Veterans
Parkway) and Interstate I-55. The project included a shift
and realignment of the southbound lanes, as well as an increase
of lanes from four lanes to six. Included in the project as
well was new construction and alignment of a ramp, and also
the widening of Veterans Parkway. Along with a major paving
project there was substantial Earthwork and bridge removal
and construction. The project required over 20 stages in order
to complete the work with minimal disruptions to traffic.
All interstate lane closures were only permitted between 8
PM and 6 AM. Do to the tight time frame, we suggested multiple
proposals, which were utilized and reduced the length and
cost of the project for the owner.
Project Technical Overview
• 104,000 S.Y. Pavement Removal
• 240,000 S.Y. Porous Granular Embankment Sub Grade
• 205,000 S.Y. Stabilized Sub-base
• 105,000 S.Y. Continuous Reinforcement PCC Pavement
• 535,000 C.Y. Earth Excavation
• 365,000 C.Y. Borrow Excavation
• 2,362 C.Y. Concrete Structure and Superstructure
• 85,000 S.Y. PCC Jointed Pavement
|