Owner: Missouri Department of Transportation
Contract Amount: Approximately $30 Million
Location: Route 50, Moniteau County:
Description: This project consists of grading,
drainage, PCC paving from Route K to a half mile west of Route
D near St. Martins. The total length of the improvement is
approximately 10.9 miles. Construction begins, March 12th
2007 and has a completion date of December 31, 2008. The purpose
of the project is to upgrade the current two lane Rt. 50 into
a four lane highway, improving traffic flow just outside of
Jefferson City.
Project Technical Overview
• 3,345,846 CY Earth Excavation
• 433,929 SY at 18in. Rock Base
• 2,740,062 CY Compacting Embankment
• 306,904 SY at 8in. Concrete Paving
|